The current westbound lane closure of Glenwood Avenue from the westerly driveway of Branan Towers to Moreland Ave will remain in place through April 9, 2021, as weather permits and with no unforeseen construction challenges.
The detour route for the Glenwood Avenue westbound closure is as follows:
-
Turn left onto Brownwood Avenue SE
-
Turn right onto Portland Avenue SE
-
Turn right onto Moreland Avenue SE to Glenwood Avenue SE.
Current plans call for “Businesses Open” signs (see attached sample) to be installed this week, possibly tomorrow (Thursday, February 25), near your businesses on Glenwood Avenue.
Work planned during the closure includes:
- IN FRONT OF THE TIRE SHOP
-
Driveway demolition, grading, concrete pouring and curing
-
Catch basin construction
-
Sidewalk demolition, grading, concrete pouring and curing
IN FRONT OF THREE (3) BUSINESSES ON GLENWOOD AVENUE BETWEEN THE TIRE SHOP AND BRANAN TOWERS
-
Driveway demolition, grading, concrete pouring and curing
-
Removal of existing driveway curb and installation of new curb
-
Sidewalk demolition, grading, concrete pouring and curing
[NOTE: Currently, work requiring the sidewalk closure in front of the three (3) Glenwood Avenue businesses is scheduled to take place between March 15-26, 2021, weather permitting and with no unforeseen construction challenges. Compensation is not provided for disruptive activities associated with public-funded infrastructure improvements.]
IN FRONT OF THE BRANAN TOWERS